In September 2004, the post-repair launch of power unit No. 5 was carried out, in which a full-scale reconstruction of the automated process control system was carried out. As a result, by September, two power units of the power plant were already equipped with the most modern equipment.
Key features of the project
In September 2004, the post-repair start-up of power unit No. 5 was carried out, where a full-scale reconstruction of the automated process control system was carried out. As a result, by September, two power units of the power plant were equipped with the most modern equipment.
- Receiving and displaying events and measurements with guaranteed quality, recording the time of the event/measurement and the time of information delivery;
- Processing telemetry information and storing it in archives;
- Prompt (brief) or complete provision of information on automation objects in the form of diagrams (using MODUS software), graphs, documents, dynamic sets of graphs, reports to operational personnel;
- Performing calculations in the built-in language of technological programming;
- Manual data entry;
- Dispatcher notes on diagrams;
- Remote control;
- Generation and automated distribution of reports;
- Maintenance of reference data (passports) of equipment of automation objects;